Safely Delivered Shipment Of Equipment For Dakrong 04 Hydropower Project

13/08/2018

Project Information

Safely Delivered Shipment Of Equipment For Dakrong 04 Hydropower Project

Vantage has successfully delivered the shipment of draft tube equipment from Lilama factory in Binh Duong province to Dakrong 04 hydropower project in Quang Tri province.

The shipment included 10p package with lot of oversized units, of which, the biggest is unit’s dimension are up to 6,4mLx2,15mWx3,7mH, which was trucked within 5 days, from 2nd – 6th August, 2018.

Solution Project Logistics